How Long Does It Take to Build a Website? Real Timelines
Quoted build times for 5-page, 10-page and e-commerce sites, plus the content, launch and Google steps that decide when a website really goes live.
Murad Raza
Freelance Full-Stack Developer

With a freelancer and the content ready, a small business website takes a few days to a few weeks to build, depending on how many pages it has and whether it sells online. My packages give a concrete reference point: a site of up to 5 pages has a 3 to 5 day quoted turnaround. A WooCommerce or Shopify store of up to 20 pages has 20 to 25 days. Those are quoted turnarounds for the build. The time before it (content and decisions) and after it (domain setup and Google finding the site) is where most projects stretch.
I have been building client websites since 2022, mostly on WordPress. I have not tracked project lengths as a formal dataset, so the timelines below are the turnaround times published on my site, and the launch steps come from official Google, Shopify and WordPress documentation linked inline.
Key Takeaways
- A 5-page site can be built in under a week; an online store takes closer to a month because of products, payments and shipping.
- The build is rarely the slow part. Missing content, slow feedback and new pages added mid-project can each push the date back.
- A connected domain can take up to 48 hours to go fully live on Shopify, so do not plan a launch for the same afternoon.
- Google can take a few days to a few weeks to crawl new or changed pages, with no guarantee of instant inclusion.
Typical timelines by type of website
The biggest factor is scope: how many pages, and whether the site has to take payments. This is how that plays out in the three website packages on my pricing page:
| Package | What it includes | Quoted turnaround |
|---|---|---|
| Starter | Up to 5 pages, basic on-page SEO, one round of revisions | 3 to 5 days |
| Business | Up to 10 pages, blog setup, advanced on-page SEO, two rounds of revisions | 7 to 10 days |
| Premium / E-commerce | Up to 20 pages, WooCommerce or Shopify, up to 30 products, payment and shipping setup | 20 to 25 days |
A store takes roughly two to three times as long as a business site. Every product needs a title, photos, a price and a description. Payment and shipping rules have to be set up and then proved with test orders. DIY site builders and agency or custom builds follow different timelines, so treat these as freelancer figures.
What happens in each phase
1. Scope and content
Before anything is built, you agree on the page list and gather the content: text, logo, photos, and for a store, a product sheet. A quoted turnaround assumes the material is ready. If you are still writing your About page, the clock is not really running yet.
2. Design and build
This is rarely the slowest part. The software install itself is not the bottleneck: the WordPress installation guide says installing WordPress "takes less than five minutes to complete." The days go into layout, mobile versions of every page, forms and basic SEO.
3. Revisions
Starter includes one revision round and Business two. Rounds go quickest when one person collects all feedback into a single list.
4. Testing
Before launch, the site gets checked on phones and desktops, forms get test submissions, and store checkouts get test orders. Speed is worth checking too. Google's Core Web Vitals guidance on web.dev sets "good" as the main content appearing within 2.5 seconds (Largest Contentful Paint). The page should also respond to a tap within 200 milliseconds (Interaction to Next Paint), and the layout should barely jump while loading (Cumulative Layout Shift of 0.1 or less). The W3C's Easy Checks page gives a quick first accessibility review anyone can run.
5. Launch and domain
Pointing your domain at the new site is not instant. Shopify's guide to connecting a third-party domain warns that "it might take up to 48 hours for your domain to be fully live." Launch early in the week, not the night before a promotion.
6. After launch: Google
A live site is not the same as a site in search results. Google's page on asking Google to recrawl your URLs says "crawling can take anywhere from a few days to a few weeks," and that requesting a crawl does not guarantee quick inclusion. Its SEO Starter Guide adds that some changes take effect in a few hours while others could take several months.
What slows a website project down
Few causes of a slipped deadline are technical:
- Content arrives late. Text, photos and product details are easy to underestimate.
- Too many decision makers. When several people approve each change, every revision round waits on the slowest reply.
- Scope grows mid-build. "Can we add a booking page?" is new work, and it moves the date.
- Account access. Domain logins, hosting access and payment provider sign-ups often sit with someone who is hard to reach. Find them before the project starts.
How to get your website live faster
You control more of the timeline than the developer does. Before the project starts:
- Write down every page you need, with one sentence on what each page is for.
- Gather your logo, photos and written content into one shared folder.
- Pick one person to give feedback and sign off.
- Confirm you can log in to your domain registrar.
- For a store, prepare a spreadsheet with each product's name, price, description and photo file names.
With that ready, a Starter-sized site is built within its 3 to 5 day turnaround, plus up to 48 hours if the domain is being connected. If you are weighing who to hire for the job, my comparison of hiring a freelance developer vs an agency covers how each tends to handle timelines.
Plan the launch date backwards
Start from the date you need the site live and work back through domain changes, testing, revisions and the build. If that leaves no room for content, start the content first. For a fixed price and turnaround on a WordPress, Shopify or WooCommerce build, see my web development services, or send me your project details and you will hear back within two business days.
Frequently asked questions
01Can a website be built in a week?
02How long until a new website shows up on Google?
03Does choosing WordPress or Shopify change the timeline?
Need this fixed on your site?
I Build Websites That Work as Hard as You Do


